Trash Daddies
Demolition7 min read

Do you need a permit to demolish a house in Toronto?

Yes. Taking down a house in Toronto takes a demolition permit, and a few other steps before the first wall comes down. Here's what's involved.

By The Trash Daddies · Updated

The demolition permit

Toronto Building issues a residential demolition permit for demolishing an existing house so a new one can be built. The application typically includes:

  • The Application to Construct or Demolish form
  • A survey or grading plan showing the existing house, property lines and lot area
  • The owner's acknowledgement of demolition control conditions
  • A municipal road damage form

If you're demolishing without building a replacement, Toronto asks you to contact the district building office first. The City's demolition permit application checklist also tells you whether a structural engineer is needed and whether extra environmental requirements apply.

Heritage properties

If the property is designated under the Ontario Heritage Act, you need a heritage permit before any changes, including demolition, and it may require a heritage impact assessment. Check the City's heritage register early.

Utilities

Gas, hydro and water have to be disconnected at the street before a full demolition. Book these early, because utilities set their own schedules.

Asbestos and designated substances

Ontario requires the owner to identify designated substances such as asbestos, lead and silica before demolition, and pass that list to the contractor (IHSA). Homes built before 1990 should have a designated substance survey. Read our asbestos guide.

What about interior demolition?

A non-structural strip-out, like cabinets, flooring or drywall with no change to the layout, generally doesn't need a permit. Removing walls or structure does. If you're not sure, we'll confirm it during our site visit.

How we help

Our house demolition service starts with a site visit where we confirm what your project needs, then we cap the plumbing and electrical in-house, take the structure down, and leave the lot clean for your builder.

Questions

Do I need a permit to demolish a house in Toronto?

Yes. Full house demolitions need a demolition permit from Toronto Building.

Do I need a permit for interior demolition?

A non-structural strip-out generally doesn't. Removing walls or structure does.

Is an asbestos survey required?

Ontario requires owners to identify designated substances like asbestos before demolition. Homes built before 1990 should be surveyed.

Get a free quote

437-288-5994Free quote
CallFree quote